Things You'll Need:
- Form for concrete to be poured into
- Hydraulic cement
- Sand & gravel
- Concrete mixer
-
Step 1
Build the form that the cement will be poured into and anchor this form under water where you wish your concrete.
-
Step 2
Mix your hydraulic concrete as per the manufacturer's instructions--this is generally 1 part cement to 2 parts sand to 4 parts gravel. Add enough water to make a thick paste, just slightly thicker than pancake batter.
-
Step 3
Pour your hydraulic concrete into your underwater form rather quickly after mixing, as the hydraulic form of cement sets up more quickly than normal cement.
-
Step 4
Protect your poured concrete from strong waves or currents as much as possible. Allow the concrete to cure for 48 hours before removing the form. Allow to cure for 7 days before placing your concrete under stress.