Things You'll Need:
- Shovel Wheelbarrow Gravel Rake Asphalt aggregate Asphalt cement Asphalt spreader Crushed gravel Paving machine
-
Step 1
Dig a base for your paved area. You will need to dig down approximately 8" in order to accommodate both the paving and the sub-base.
-
Step 2
Pour a 5-6" layer of loose gravel into the hole you have prepared. Use a wheelbarrow to transport the gravel and a rake to spread it out so that it is fairly even.
-
Step 3
Top off the loose gravel with a 1" to 2" layer of aggregate, composed of sand and rocks.
-
Step 4
Pour the hot asphalt mix (typically it is purchased from a paving contractor and delivered in large drums) onto your aggregate base, then spread it across the area using an asphalt spreader.
-
Step 5
Apply a thin layer of crushed gravel to the asphalt while it is still hot, then drive a paver over the surface until it is smooth and level.