Things You'll Need:
- Concrete
- Gravel
- Re-bar
- Several dozen bricks or half bricks
- Wire Mesh
- 4 mil plastic sheets
- Digging tools
- Bubble Level
- Trowel
- 1/2 inch thick 8 inch wide by 10 foot long framing Boards
- Several wooden stakes
-
Step 1
Level the area where you intend to pour your foundation. It is not necessary for the pad of a slab foundation to be perfectly level, but your pad area should be fairly level. Making your pad level right from the start will save you time and headaches later.
-
Step 2
Dig a trench all the way around the perimeter of your foundation. This trench will be an important part of your foundation. It should be a minimum of 6-inches wide and 24-inches deep. If the ground in your area typically freezes in the winter, your foundation trench needs to be deeper than the permafrost line. If you are building a house that is two or more stories tall then your foundation trench will need to be wider than 6-inches; check local building codes for the exact width required for your geographic area and soil conditions.
-
Step 3
Build a frame all the way around your trench using your 1/2 inch thick 8-inch wide and 10-foot long boards. Hold the boards in place with wooden stakes. Your foundation frame will be built on both sides of your trench, in effect raising your trench 8-inches above the level of the ground. Using long boards and a good level, make certain that your foundation frame is perfectly level. This may require that you lower or raise sections of the frame. Start at one corner of your foundation frame and work out from there. It is vital that your entire frame is level.
-
Step 4
Place bricks in the bottom of your trench spaced in such a way that you can lay two rows of re-bar in your trench with the re-bar supported by the bricks. Fill your trench with cement all the way to the top. Smooth the top with a trowel if necessary.
-
Step 5
Remove your foundation framing boards. Fill the inside area of your pad with gravel 4-inches deep. Place your 4-mil plastic sheets on top of the gravel to act as a moisture barrier. Use bricks or small pieces of stone to form a base on which you can lay your wire mesh. Fill the entire inside of your pad area with cement. Your cement should be approximately 4-inches thick and match the height of your trench foundation perfectly. Smooth with a trowel if necessary. Allow to harden.