Step1
Determine how many squares of three-tab shingles you need to purchase and install. A square is equal to 100 square feet of roof space. Add up the total square feet of roof space and divide by 100 for the number of squares needed. Add a 10 percent cushion.
Step2
Cut the tabs off enough shingles to create one row of tab-less shingles across the roof.
Step3
Measure the roof and place a chalk line in the middle of the roof from top to bottom.
Step4
Go to the middle of the roof at the roof's edge.
Step5
Lay down the start line for the shingles with the shingles you just cut. Center the first shingle on the chalk line. The uncut side of the shingles will need to hang over the edge of the roof by 5/8 inch.
Step6
Make sure the first shingle is perfectly aligned and then use four nails to secure the shingle. Place a nail approximately 1 inch from each side and then place the other two nails equidistant from each other in the middle of the shingle.
Step7
Work your way across the roof laying down the start line of shingles, making sure your line is perfectly straight. Shingles should butt up against each other.
Step8
Cut shingles to size when you reach the edge of the roof or a ridge.
Step9
Lay your first full shingle centered on the center line on the roof with the tabs facing down and lining up with the bottom of the starter line.
Step10
Use four nails to install the three-tab shingles. The nails go approximately 2 inches above the tabs with one nail near each side and two nails equidistant from the outside nails.
Step11
Lay the shingles across the roof along the first line of starter shingles.
Step12
Start the second row of shingles at the chalk line in the middle of the roof with a shingle just to the left or right of the chalk line. The tabs of the second row should lay directly in the middle of the gap in the tabs on the preceding row.
Step13
Finish the row of shingles.
Step14
Continue laying rows of shingles starting at the center chalk line and alternating between placing the first shingles directly on the line and just to the side of the line.
Step15
Add the ridge caps.